MALTON COMMUNITY CENTRE

We are proud to have completed the electrical renewal project at the Malton Community Centre in Mississauga, a major initiative focused on modernizing one of the city’s key public facilities. This multi-phase commercial project included comprehensive electrical upgrades that enhanced functionality, safety, and long-term infrastructure reliability.
In Phase 1, we completed electrical upgrades for the library, installed a new library desk, added new washrooms with upgraded lighting and electrical systems, and integrated security gates and data outlets to improve safety and connectivity.
Phase 2 involved the installation of a new 1600A electrical service, construction of a concrete-encased duct bank, installation of a precast transformer vault, and protective bollards.
In Phase 3, we replaced main switchboards, panelboards, distribution panels, and a transformer to improve system capacity and performance.
Phase 4 included the installation of a dedicated 600A service for mechanical units, ensuring reliable operation of critical building equipment.